The impacted areas are as follows:Baldwin Avenue from Beechnut to Ione4300 Block of all side streets crossing Baldwin
Storm Sewer Pipe, Sanitary Sewer Pipe Rehabilitation and CenterPoint Energy Gas Line Relocation... Read on...
Beginning Monday, May 21, 2012 - Thursday, May 31, 2012, construction hours will be extended until 10:00 pm each day to facilitate Sanitary Sewer Rehabilitation operations from Oleander to Edith on Baldwin Avenue. Please see the additional information.
The intersection of Mildred and Baldwin will be under construction and closed to traffic northbound and southbound beginning May 21, 2012. Please see the additional information.
The intersection of Vivian and Baldwin will be under construction and closed to traffic northbound and southbound beginning May 14, 2012. Please see the additional information.
The intersection of Effie and Baldwin will be under construction and closed to traffic northbound and southbound beginning May 7, 2012. Please see the additional information.
The intersection of Darsey and Baldwin will be under construction and closed to traffic northbound and southbound beginning April 30, 2012. Please see the additional information.
The intersection of Valerie and Baldwin will be under construction and closed to traffic northbound and southbound beginning April 23, 2012. Please see the additional information.
The intersection of Cynthia and Baldwin will be under construction and closed to traffic northbound and southbound beginning April 9, 2012. Please see the additional information.
The intersection of Dorothy and Baldwin will be under construction and closed to traffic northbound and southbound beginning April 2, 2012. Please see the additional information.
The intersection of Holt and Baldwin will be under construction and closed to traffic northbound and southbound beginning March 23, 2012. Please see the additional information.
The intersection of Lafayette and Baldwin will be under construction and closed to traffic northbound and southbound beginning March 12, 2012. Please see the additional information.
Dear Friends of Patrons for Bellaire Parks,
Please join us for a Ribbon Cutting Ceremony dedicating the Bellaire Town Square Entry Plaza. Light refreshments will be served. Thank you to all donors and supporters of... Read on...
The Elaine Wood Therapy Pool will be open at 7 am Monday - Friday this summer for your aquatic therapy needs. Follow the link for complete pool hours and information.
The City of Bellaire is pleased to announce the launch of an effort by the Building and Standards Commission to share information about sustainable building practices. These practices aim to conserve resources and reduce... Read on...
In Observance of Memorial Day, Monday, May 28, 2012, City Facilities Will Be Closed. No garbage collection on Memorial Day. Monday's Garbage collection will continue on your next regularly scheduled pick-up day.
The Bellaire Parks & Recreation Recreation Survey deadline has been extended until May 31. Please follow link to complete survey. Thank you.
The Bellaire Police Department wants citizens to be aware of two incidents which occurred this week.
The first is an incident that occurred in the 5400 block of Braeburn on Saturday January 14th at approximately 10:35 PM.... Read on...